Facility Details
View DataCategory | Office: Mixed-Use Office |
---|---|
Electric Utility | Consolidated Edison |
Gas Utility | Consolidated Edison |
NYISO Zone | J - New York City |
-
Program CHP Developer/Installer RSP Systems Data Monitoring Apr 2018 – Mar 2023 NYSERDA Contract Name Hudson Yards Tower C ConEd Target Zone Heat Recovery Loads Met Other Heat Loads System Redundancy (N+1) Grid Export Capable Project Documentation
-
Unit Manufacturer Capstone Turbine Corporation Unit Model C200 Elec. Gen. Rating per Unit 200 kW Thermal Gen. Rating per Unit 874.8 MBtu/h No. of Units 6 No. of Prime Movers 6 Primary Fuel Natural Gas Prime Mover Microturbine Rated Electric Efficiency (% HHV) 28.0 Rated CHP Efficiency (% HHV) 67.0
-